SECTION 153 OF THE PLANNING ACT 2008
REGULATION 6 OF THE INFRASTRUCTURE PLANNING (CHANGES TO, AND REVOCATION OF, DEVELOPEMNT CONSENT ORDERS) REGULATIONS 2011 NOTICE OF APPLICATION TO MAKE A NON-MATERIAL CHANGE TO THE FOLLOWING DEVELOPMENT CONSENT ORDER:
THE DOGGER BANK CREYKE BECK OFFSHORE WIND FARM ORDER 2015 (AS AMENDED) (S.I. 2015/318)

  1. An application has been made by Doggerbank Offshore Wind Farm Project 1 Projco Limited (“Projco 1”) and Doggerbank Offshore Wind Farm Project 2 Projco Limited (“Projco 2”) (together the “Applicant”) to the Secretary of State for Energy Security and Net Zero to make a non-material change (“NMC”) to the above mentioned Development Consent Order (the “DCO”).
  2. The DCO granted development consent to Doggerbank Project 1 Bizco Limited (“Bizco 1”) for “Project A” and Doggerbank Project 4 Bizco Limited (“Bizco 4”) for “Project B” – two offshore wind turbine generating stations each comprising up to 200 wind turbine generators and associated development in the Dogger Bank Zone and the East Riding of Yorkshire. Bizco 1 was renamed at Companies House as Projco 1, and Project A was renamed Dogger Bank A (herein “DBA”). Bizco 4 was renamed at Companies House as Projco 2 and Project B was renamed Dogger Bank B (herein “DBB”).
  3. The application seeks to make non-material changes to the drafting of the DCO by amending the wording of certain definitions, articles and paragraphs of schedules to allow DBA and DBB to be considered separately, and for the discharge and enforcement of each project’s relevant requirements to be distinct from the other project.
  4. The contact details of the Applicant are: Doggerbank Offshore Wind Farm Project 1 Projco Limited and Doggerbank Offshore Wind Farm Project 2 Projco Limited at No. 1 Forbury Place 43 Forbury Road, Reading, United Kingdom, RG1 3JH.
  5. Email contact is possible by contacting: DoggerBankConsentsConsultations@sse.com.
  6. The application documents and details of the changes proposed by this NMC Application are available for inspection, free of charge, at the “Documents” tab on the National Infrastructure Planning Portal’s Dogger Bank Creyke Beck page here: https://national-infrastructure-consenting. planninginspectorate.gov.uk/projects/EN010021
  7. For general enquiries on how to obtain any of the documents or on the information contained within them, please contact Dorothee Neun at the Applicant (dorothee.neun@sse.com or 0141 224 7248).
  8. A free digital copy of the application documents can also be obtained from the Applicant using the contact details provided above. This will be available until the deadline for responses set out below closes. Alternatively, a paper copy can be obtained from the Applicant for a charge of £300.
  9. Please send any representations about the application by email to the Planning Inspectorate at: dbcreykebeck@planninginspectorate.gov.uk or in writing to: Major Applications & Plans, The Planning Inspectorate, Temple Quay House, 2 The Square Temple Quay, Bristol BS1 6PN. Please quote ‘Dogger Bank Creyke Beck’ on any correspondence. Any representations received by the Secretary of State in response to the consultation will be published on the Planning Inspectorate’s Infrastructure Planning Portal (https://national-infrastructure-consenting. planninginspectorate.gov.uk/) with all personal information removed.

10. The deadline for receipt of representations is 23:59 on 5 May 2025.

Doggerbank Offshore Wind Farm Project 1 Projco Limited and Doggerbank Offshore Wind Farm Project 2 Projco Limited


Find more public notices at Fishing News